300D Boiler Building

As-built drawings for a steel-framed boiler house, with a new 2-ton crawl beam

Structural steelCrawl beam designAs-built drawings
04
300D Boiler Building, 3D model
Problem statement

The project was abandoned after the previous contractor cast the concrete surface bed in the wrong direction. The original design also had no crawl beam, so there was no way to hoist the boilers in and out.

Scope

What I was asked to deliver

As-built drawings of the boiler house as it stands, plus the design of a 2-ton crawl beam for hoisting the boilers.

Solution

How I solved it

  1. Drew the as-built structure to match what was on site: UC254 × 254 × 107 columns on the existing 600 × 600 plinths, facebrick to +4.016 m with perforated plate above, and an 11° mono-pitch Kliplok roof on 100 mm C-purlins and light steel trusses.
  2. Reconfigured the bracing (Rev 2).
  3. Designed a 2-ton crawl beam, a UC203 × 203 × 46 with its connections to the frame, for hoisting the boilers (Rev 3).
  4. Issued plan, four elevations, structural layout, four grid elevations and connection details.
3D model

Watch it go together

Build sequence
Drag to orbit · scroll or pinch to zoom · right-drag to pan
Drawings

Plans, elevations & sections

East elevation
East elevationmm
Ground level plan
Ground level planmm
Roof plan
Roof planmm
West elevation
West elevationmm
South elevation
South elevationmm
North elevation
North elevationmm
Section — grid 3-3 to 4-4
Section — grid 3-3 to 4-4mm
Drawing set as issued

The original fabrication & construction sheets

East elevation
East elevation
Structural layout — 3D, plans & connection details
Structural layout — 3D, plans & connection details
Grid C-C
Grid C-C
Ground level plan
Ground level plan
West elevation
West elevation
South elevation
South elevation
North elevation
North elevation
Grid D-D
Grid D-D
Grid 3-3
Grid 3-3
Grid 4-4
Grid 4-4